Receipt, storage & installation planning

Agree how the delivered parts will be checked, stored and installed against the approved project documents.

Use this planning checklist with the current order drawings and project-specific instructions. It is not a structural design, a universal fixing schedule or an installation approval.

Before dispatch

Agree the configuration, drawing revision, part and package marks, quantities and documents required. Define who checks the finished parts and who accepts the delivery. State site handling constraints and any packing sequence needed.

At receipt

Compare the packing list, package/part labels and quantities with the accepted order. Record visible damage, missing parts or document discrepancies and retain photographs and package marks for review. Quarantine disputed parts as appropriate rather than changing them to fit before the issue is reviewed.

Before installation

Confirm the current layout, support arrangement, bearing direction, openings and edge details. Check that the supplied fixing function and material match the intended joint and support. Joining clips are not automatically hold-down clips. Obtain the applicable fastening instructions; no universal clip quantity or torque is specified here.

Storage, handling and site changes

Agree handling, support, stacking and storage instructions for the actual panels and profiles. Review site cuts, new holes or substitutions against the approved configuration before proceeding. Do not infer safe lifting points, stacking limits or working loads from a product photograph.

Keep a traceable handover

Retain the accepted drawing revision, part list, inspection and document records. Record site changes and open items with the responsible reviewer. Installation and local regulatory acceptance remain within the agreed project responsibilities.